The Delhi Metro Rail Corporation Ltd. DMRC, is a Centre-state Public Sector company that operates the Delhi Metro. It was established on 3 May 1995 in New Delhi. The DMRC is also involved in the planning and implementation of metro rail, monorail, and high-speed rail projects in India and abroad.

DMRC Phase III Projects

Majlis Park - Shiv Vihar

Length 58.596 km (39.479 km Elevated, 19.117 km Underground). Total stations 38 (Elevated 26, Underground 12).
Progress of civil works upto October 2015 is 77.11%.
The line is targeted for completion in December 2016.

Janakpuri West - Botanical Garden

Length 34.273 km (10.466 km Elevated, 23.807 km Underground). Total stations 23 (Elevated 8, Underground 15).
Progress of civil works upto November 2015 is 81.09%.
The line is targeted for completion in December 2016.

Central secretariat - Kashmere Gate

Length 9.370 km (Underground).
Total stations 7 (Underground).
Progress of civil works upto November 2015 is 90.57%.
The line is targeted for completion in March 2016.
A stretch of 3.03 km between Central Secretariat-Mandi House has already been opened to public on 26.06.2014.
Another stretch of 0.972 km from Mandi House – ITO has been opened on 08.06.2015.

Jahangirpuri - Samaypur Badli

Length 4.489 km (Elevated).
Total stations 3. (Elevated).
Work is completed.
The line has been commissioned on 10.11.2015.

Badarpur - Escorts Mujesar

Length 13.875 km (Elevated).
Total stations 9 (Elevated).
Work is completed.
Line has been opened for public by Hon’ble PM of India on 06.09.2015.

Dwarka – Najafgarh

Length 4.295 km (2.754 km Elevated, 1.541 km Underground). Total stations 3 (Elevated 2, Underground 1).
Progress of civil works upto November 2015 is 50.62%.
The line is targeted for completion in December 2016

Mundka – Bahadurgarh

Length 11.182 km (Elevated).
Total stations 7 (Elevated).
Progress of civil works upto November 2015 is 60.54%.
The line is targeted for completion in December 2016



Quick Reply
Your Username: Click here to log in

Message:
Options



All times are GMT +5. The time now is 10:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Content Relevant URLs by vBSEO 3.6.0

1 2 3 4 5 6 7 8